The project scope consisted of the complete construction of a new pumping station, including all deep well dewatering, sheeting, excavation, reinforced concrete substructure (including wet wells and dry wells), masonry building, and a precast concrete roof erected on structural steel. PKF was also contracted to supply and install all mechanical and electrical components, back-up power generation system, odor control system, and all site improvements.
#246 | CROSS KEYS PUMP STATION
Berlin, NJ
Owner: |
CAMDEN COUNTY MUNICIPAL UTILITIES AUTHORITY |
Engineer: |
D&B ENGINEERS AND ARCHITECTS |
Cost: |
$13,172,000.00 |