#225 | Baxter Generators

Philadelphia , PA


Owner:

City of Philadelphia, Water Department
   

Cost:

$6,200,000.00

This project involved two major elements of work. The most significant was the upgrade of the existing DCS system with new equipment, fiber optic cabling and new instrumentation. New workstations and elevated floor systems for new cabling were also installed. The completion of this work required continuous coordination with plant personnel to assure minimal disruption in plant operations. The second element of work involved the installation of 48 new level sensors at the 94 filters in the filter building.